The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

What makes up a #BroadwaySubwayProject station? Beneath the station entrance building, the underground concourse level will connect the station entrance to the SkyTrain platform level below. #BSPStationSpotlight

What makes up a #BroadwaySubwayProject station?

Beneath the station entrance building, the underground concourse level will connect the station entrance to the SkyTrain platform level below.

#BSPStationSpotlight
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Crews are building the train platform at the future South Granville Station. This is where passengers will wait for their next SkyTrain. The tracks will be built along each side, with the platform in the middle.

Crews are building the train platform at the future South Granville Station.

This is where passengers will wait for their next SkyTrain. The tracks will be built along each side, with the platform in the middle.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

What makes up a #BroadwaySubwayProject station? The lowest level of the subway station is where transit users will find the SkyTrain platform to board the SkyTrain! #BSPStationSpotlight

What makes up a #BroadwaySubwayProject station?

The lowest level of the subway station is where transit users will find the SkyTrain platform to board the SkyTrain!

#BSPStationSpotlight
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Each #BroadwaySubwayProject station is built using these 5 steps. To learn more about how we build the subway stations, visit: ow.ly/hFQJ50T1kFo

Each #BroadwaySubwayProject station is built using these 5 steps.  

To learn more about how we build the subway stations, visit: ow.ly/hFQJ50T1kFo
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Crews pour concrete to construct the second section of roof at Great Northern Way-Emily Carr Station. This section of roof is for the underground portion of the station. This is part of Step 3 of station construction. Learn more: ow.ly/KjNg50T73OM

Crews pour concrete to construct the second section of roof at Great Northern Way-Emily Carr Station. 

This section of roof is for the underground portion of the station. 

This is part of Step 3 of station construction. Learn more: ow.ly/KjNg50T73OM
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

The #BroadwaySubwayProject is building 6 new underground stations at: -Great Northern Way–Emily Carr -Mount Pleasant -Broadway–City Hall -Oak–VGH -South Granville -Arbutus To learn more about each of the stations, visit: ow.ly/f08250T1ln9

The #BroadwaySubwayProject is building 6 new underground stations at:
-Great Northern Way–Emily Carr
-Mount Pleasant
-Broadway–City Hall
-Oak–VGH
-South Granville
-Arbutus

To learn more about each of the stations, visit: ow.ly/f08250T1ln9
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Tunnel Boring Machines Phyllis and Elsie say goodbye to Vancouver. Watch as they are dismantled and removed at Cypress St. between March and July 2024. To see more photos and videos of the project, visit: ow.ly/nVju50T86PB

The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Before a base slab foundation is poured, waterproofing & rebar are installed. The waterproof layer keeps the station dry while the layers of concrete & rebar make the foundation strong. This is part of the 1st step of station construction. Learn more: ow.ly/6KN650T4kbF

Before a base slab foundation is poured, waterproofing & rebar are installed. 

The waterproof layer keeps the station dry while the layers of concrete & rebar make the foundation strong. 

This is part of the 1st step of station construction. Learn more: ow.ly/6KN650T4kbF
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Looking east towards the elevated guideway, you can see the tunnel entrance near the future Great Northern Way-Emily Carr Station. With construction of the elevated guideway now complete, work in this area has shifted to track installation.

Looking east towards the elevated guideway, you can see the tunnel entrance near the future Great Northern Way-Emily Carr Station. 

With construction of the elevated guideway now complete, work in this area has shifted to track installation.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Each TBM broke through the east wall of each station on their journey to Cypress St. Here, TBM Elsie underwent scheduled maintenance & was moved across the station’s completed base slab foundation before departing again. All TBM breakthroughs are now complete!

Each TBM broke through the east wall of each station on their journey to Cypress St.

Here, TBM Elsie underwent scheduled maintenance & was moved across the station’s completed base slab foundation before departing again.

All TBM breakthroughs are now complete!
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Once tunnelling is complete, new columns, walls and floors are built. A roof is constructed on top of the underground station. Here, a worker inspects the rebar on a wall. This is part of step 3 of the station construction process: ow.ly/klVG50T4nWr

Once tunnelling is complete, new columns, walls and floors are built. A roof is constructed on top of the underground station.

Here, a worker inspects the rebar on a wall.

This is part of step 3 of the station construction process: ow.ly/klVG50T4nWr
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

At GNW-Emily Carr Station, crews are building the underground station’s roof. The second roof section, unfinished in this photo, was completed in late July. Once the #BroadwaySubwayProject is complete, everyone will be able to walk, bike, roll or drive above these roof sections.

At GNW-Emily Carr Station, crews are building the underground station’s roof. The second roof section, unfinished in this photo, was completed in late July. Once the #BroadwaySubwayProject is complete, everyone will be able to walk, bike, roll or drive above these roof sections.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Station construction is underway at all 6 stations along the #BroadwaySubwayProject alignment. Here are the 5 steps of station construction! To learn more about station construction, visit: ow.ly/vFJi50ThBA6

Station construction is underway at all 6 stations along the #BroadwaySubwayProject alignment. 

Here are the 5 steps of station construction!

To learn more about station construction, visit: ow.ly/vFJi50ThBA6
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Did you know that each new Broadway Subway station will feature up and down escalators? The first escalator trusses, which house the electrical and mechanical equipment, were installed at South Granville Station in July. An elevator will later be constructed to the left.

Did you know that each new Broadway Subway station will feature up and down escalators?

The first escalator trusses, which house the electrical and mechanical equipment, were installed at South Granville Station in July. An elevator will later be constructed to the left.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Curious about what’s happening on the Broadway Subway Project? Come visit our informational pop-up! Join us near 10th Avenue at the Main St. Car Free Day on Sunday September 15th, from 12:00 pm – 7:00 pm.

Curious about what’s happening on the Broadway Subway Project? Come visit our informational pop-up!

Join us near 10th Avenue at the Main St. Car Free Day on Sunday September 15th, from 12:00 pm – 7:00 pm.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

How many crew members can you spot in this photo? Crews install metal beams to prepare for construction of the concourse-level floor. This scaffolding system will allow crew members to install rebar for the next level floor and supports the weight of the concrete pour.

How many crew members can you spot in this photo?

Crews install metal beams to prepare for construction of the concourse-level floor. This scaffolding system will allow crew members to install rebar for the next level floor and supports the weight of the concrete pour.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Wondering what’s happening on the Broadway Subway Project? Come visit our informational pop-up! Join us tomorrow, September 18th from 11 am – 2 pm, at 1455 W. 10th Avenue in front of the Firehall Library.

Wondering what’s happening on the Broadway Subway Project? Come visit our informational pop-up!

Join us tomorrow, September 18th from 11 am – 2 pm, at 1455 W. 10th Avenue in front of the Firehall Library.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

This tunnel, underneath the Canada Line tracks, will connect passengers who are transferring from the future Millennium Line platform to the Canada Line platform at Broadway City-Hall. Here, crews had completed the first out of four concrete rings for the tunnel structure.

This tunnel, underneath the Canada Line tracks, will connect passengers who are transferring from the future Millennium Line platform to the Canada Line platform at Broadway City-Hall.

Here, crews had completed the first out of four concrete rings for the tunnel structure.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Take a sneak peek at Arbutus Station’s platform level. 👀 This level is where passengers will board the SkyTrain. The platform will be constructed in the middle, where the columns are, with the tracks on either side.

Take a sneak peek at Arbutus Station’s platform level. 👀

This level is where passengers will board the SkyTrain. The platform will be constructed in the middle, where the columns are, with the tracks on either side.
The Broadway Subway Project (@broadwaysubway_) 's Twitter Profile Photo

Have questions about the #BroadwaySubwayProject construction? Call our 24/7 construction line to speak to an operator: 1-844-815-6114 For general project information, visit: ow.ly/2xtr50Tnn7O

Have questions about the #BroadwaySubwayProject construction? 

Call our 24/7 construction line to speak to an operator: 1-844-815-6114

For general project information, visit: ow.ly/2xtr50Tnn7O